Onsala (Michael Lindqvist at Sun May 30 12:22:13 2004) Success :
Some RFI.
Urumqi (yang wen jun at Sun May 30 12:43:27 2004) Success :
recorder is MKV.
Torun (K. Borkowski at Mon May 31 08:05:17 2004) Minor failures :
No known problems (see however this band feedback on linear polarization).
Westerbork (Tony Foley at Mon May 31 10:33:53 2004) Success :
Wb used in phased array mode.
Only a little RFI. Short scans deposited in JIVE
Noto (P. Cassaro at Mon May 31 21:31:00 2004) Minor failures : RECO LATE RFI
The observation begun at 9:45 UT, due to problems with the MK5 recorder. There were a lot of interferences in band.
Effelsberg (A. Kraus at Tue Jun 1 10:44:01 2004) Minor failures : RECO TSYS RFI
After the 5th scan, we had some problems with the mk5 system. The operator changed diskpacks by hand. The first 5mins of the 6th scan were lost.