CL06U1
Session: Jun 2006 (session 2)
Wavelength: 30 cm
Comment
To give feedback on this experiment, click
Experiment Feedback
Effelsberg (dgraham at Thu Jun 1 21:20:55 2006) Failure : RFI
No chance.
Torun (Kaz Borkowski at Fri Jun 2 08:11:40 2006) Failure : RFI
Tsys measurements are practically all useless due to RFI.
Westerbork (Tony Foley at Fri Jun 2 11:34:43 2006) Minor failures : RFI
Wb used in phased array mode.
Some RFI
Onsala (Michael Lindqvist at Fri Jun 2 19:29:45 2006) Success :
Done at bands free of RFI.
Noto (P. Cassaro at Fri Jun 16 22:37:41 2006) Failure : RFI
No way.
EVN experiment feedback facility: entire session
Entire Session
Session: Jun 2006 (session 2)
Wavelengths: 30cm 18/21 5 6 cm
Comment
To give feedback on this entire session, click
Entire Session Feedback
Torun (Kaz Borkowski at Mon Jun 5 12:32:29 2006) Minor failures :
This note concerns the UHF experiments only.
Shortly before the first experiment we could manage to install the Lange coupler to produce two circular polarizations instead of the linear polarization announced in the block schedule. Also, we failed to install the phase cal.
Jodrell_Bank (Alastair Gunn at Tue Jun 20 09:14:12 2006) Success : PCAL
The MkII telescope was used (Jb2).
During this session the Mk2 phase cal. signal was found to be too high and could not be easily reduced in strength. I therefore switched off the phas cal. signal for the entire session (for Mk2 only).