Entire Session
Session: Feb 2003 (session 1)
Wavelengths: 1.3 3.6 18 cm
Comment
To give feedback on this entire session, click
here
Entire Session Feedback
Cambridge (Zsolt Paragi(for A.G.) at Thu Feb 6 08:29:26 2003) Minor failures : RECO
Due to a failure of the headstack, track 30 on our VLBA
recorder (Cm) has been remapped to track 34, i.e. third system
track.
Cambridge (Zsolt Paragi(for A.G.) at Thu Feb 6 08:35:25 2003) Minor failures : RECO
Due to a failure of the headstack, track 30 on our VLBA
recorder (Cm) has been remapped to track 34, i.e. third system
track.
Effelsberg (A. Kraus at Mon Feb 10 10:02:23 2003) Failure :
Due to a crack in the azimuth track, Effelsberg is unable to attend the session.